The newly built ferry “Loch Indaal,” which had faced repeated delays due to issues at the shipyard, has finally been completed and delivered.
Recently, Turkey’s Cemre Shipyard delivered the diesel-electric Loch Indaal to Caledonian Maritime Assets Limited (CMAL), a Scottish maritime asset management company. Although originally scheduled for delivery in February 2025, the vessel’s handover was delayed by 20 months beyond the contractual date due to issues with the shipyard’s construction schedule.
The “Loch Indaal” is 95 meters long and can accommodate 450 passengers as well as 100 passenger cars or 14 commercial vehicles. It is powered by a diesel-electric propulsion system and has been certified by the UK Maritime and Coastguard Agency (MCA) and Lloyd’s Register (LR).
It is understood that Cemre Shipyard and CMAL signed contracts for the construction of four diesel-electric passenger/ro-ro ferries—two in 2022 and another two in 2023—with a total order value of approximately £200 million. The four new vessels, named “Isle of Islay”, “Loch Indaal”, “Lochmor”, and “Claymore”, were originally scheduled for delivery in October 2024, February 2025, June 2025, and October 2025, respectively.

In the early stages of the project, CMAL was highly satisfied with the construction progress of the new vessels, with several shipbuilding milestones for the first two ferries even being reached ahead of schedule.
However, this positive momentum did not last. Following the launch of the first two ferries, delays in the project began to emerge. The delivery of the “Isle of Islay”—originally slated for October 2024—has been pushed back to January 2026, a delay of 15 months. The “Loch Indaal” faces a 20-month delay, while the delivery dates for the “Lochmor” and “Claymore” have both been deferred to the second quarter of 2027.
Reports indicate that the delays to the project are largely linked to the financial difficulties faced by Cemre Shipyard.
To mitigate shipbuilding risks, CMAL had previously made construction payments to Cemre Shipyard for four new vessels, in addition to covering an extra £20 million in incremental shipbuilding costs.
To protect the shipbuilding costs already incurred, in June 2026, CMAL was forced to take an extraordinary step—it paid £23 million to assume ownership of the three ferries that Cemre Shipyard was building for it (at that time, the “Loch Indaal” had not yet been delivered). This meant that, should the Turkish shipyard unfortunately go bankrupt, CMAL, as the shipowner, would have the right to tow the vessels under construction to other shipyards to complete the remaining construction work until they were delivered and put into service.
In addition to the projects currently underway at Cemre Shipyard, the construction of “Glen Rosa”—the second LNG dual-fuel ferry commissioned by CMAL—is now eight years behind its original schedule and remains under construction at the shipyard. Regarding new shipbuilding, the owner placed an order earlier this year with CSSC Guangzhou Shipyard International (GSI) for two next-generation passenger/ro-ro (ro-pax) vessels, intended to replace aging vessels in its fleet that have been in service for nearly three decades.