On November 20, Offshore Oil Engineering Co., Ltd. (COOEC) issued an announcement stating that COOEC had recently formally signed the MM-EPIC2 turnkey project contract with QatarEnergy. The contract is valued at approximately $800 million, with a construction period of 66 months.

Under the contract, COOEC will serve as the general contractor for the MM EPIC2 project, responsible for project management, detailed design, procurement, construction, transportation, installation, pre-commissioning, and related work. The MM EPIC2 project is a key component of QatarEnergy’s series of projects for the redevelopment of the Maydan Mahzam oil field.
COOEC stated that the successful signing of this contract further enhances its market share in Qatar and highlights its strong customer recognition and market stickiness in the local market. The contract lays a solid foundation for COOEC’s overseas strategic planning for the “15th Five-Year Plan” period. It also reflects COOEC’s continued efforts to strengthen overseas market development and promote high-quality development of its international business, and represents an important manifestation of its strategic resolve.
It is understood that the MM EPIC2 project is yet another major EPC contract secured by COOEC in the Qatari market, following the BH EPIC project and the NFPS COMP5 project in Qatar. Winning this contract marks a milestone for COOEC, as the cumulative value of orders signed by its Middle East region over the past three years has exceeded 50 billion yuan (approximately $7.485 billion).

According to previous reports, COOEC signed a contract with QatarEnergy for the BH EPIC project, with a total contract value of approximately $4 billion. This contract represents the largest international offshore oil and gas engineering, procurement, and construction (EPC) project ever secured by a Chinese company in terms of contract value, scope of work, and overall construction complexity. Construction on the project began on September 15, 2026.
The BH project is located in the offshore area of the Bul Hanine oil field in Qatar and is being developed by QatarEnergy. The maximum water depth is approximately 40 meters. COOEC’s scope of work includes the construction of more than 60 new offshore oil and gas facilities and 40 subsea pipelines and cables, as well as the retrofitting of existing platforms and the decommissioning of abandoned platforms. The total volume of steel processed exceeds 130,000 tons, covering the entire project lifecycle—from engineering design, procurement, and construction to transportation, installation, and commissioning.
The owner of the NFPS COMP5 project is QatarEnergy LNG. The project was awarded to a joint venture between CNOOC and Italian offshore engineering giant Saipem, with a total contract value of approximately $4 billion, of which CNOOC’s share exceeds $800 million.
COOEC, a listed company controlled by China National Offshore Oil Corporation, is the only large-scale engineering general contracting company integrating the design, procurement, construction, offshore installation, commissioning and maintenance of offshore oil and gas development engineering, as well as liquefied natural gas, offshore wind power, refining and chemical engineering in China, and is also one of the largest and strongest offshore oil and gas engineering general contracting companies in the Asia-Pacific region.
COOEC’s latest quarterly report shows that in the first three quarters of 2026, COOEC secured a total of 27.791 billion yuan (approximately $4.160 billion) in new contracts. As of September 30, 2026, CNOOC’s total order backlog stood at approximately 72.7 billion yuan (approximately $10.883 billion).