On April 23, the first 6G50ME-C9.6-HPSCR main engine in the series built by CSSC Engine Co.,Ltd. (CSE) for COSCO Heavy Industry (Zhoushan) successfully passed all inspection items in one day for the first time, setting a new record for the company’s fastest main engine delivery. All performance indicators have been unanimously recognized by shipowners, shipbuilders, ship inspectors and MAN experts.
In this delivery, CSE firstly proposed a simplified scheme for the SCR engine test. Through rigorous technical demonstration and test verification, various test contents were successfully completed, and various performance indicators were excellent, which was recognized by the classification society. The approval of the program successfully shortened the 7-day assembly and disassembly cycle of the SCR system.
On the day of inspection, the commissioning team completed the deep cleaning of the main engine, environmental calibration of the centralized control room, confirmation of the test plan, and preparation of the customer’s data in advance before the shipowner, shipbuilder and classification society arrived.
During the entire inspection process, all test items were passed at one time, and the delivery time was at least 8 hours earlier than previous similar engines. The test results fully met the requirements of relevant parties, and the product quality and work efficiency were praised by customers.